Batch B04Checkpoint
Checkpoint B04¶
Checkpoint · Batch B04 — XY joints + X carriage
- Gate B passed before B04-P1 started
- Printed M3 holes in both XY joints and both carriage halves caliper 3.40 mm ±0.10
- (kit day) MGN12 carriage screw pattern confirmed against
x_frame_V2TR_MGN12_left/rightbefore heat-sets - (kit day) Omron probe barrel measured (8 mm vs 9 mm) — correct
probe_retainer_bracketvariant confirmed - Confirmed X-carriage is
x_frame_V2TR_MGN12_left/right(V2TR/Clockwork-2), not the superseded MGN9 carriage
Common mistakes¶
- Grabbing a superseded MGN9 X-carriage file by mistake — LDO Build Notes flag this explicitly.
V2TRis the right file: it is the carriage shared by the V2 and the Trident. - Committing heat-set inserts into the carriage before the real carriage has been offered up on kit day.
- Reaming a printed hole instead of calipering it and fixing the profile.
Next¶
Assembly: Gantry (p.82–107). Printing: B05 — Z joints + Z chain.