Tonight

Total remaining (estimate): ~59.9 h hands-on across 16 build chapters; 157.0 h of printing across 22 plates, plus 25.0 h across 5 plates of B11, outside the run (~5 min hands-on per plate start, the rest unattended).

pause Before the kit

The same planner over the timeline rows without the KIT marker, plus the individual (pre-kit) stopping points inside rows that do need the kit — the Core One+ batches and every piece of bench work that needs no Voron part.

If you have 30 min:

If you have 60 min:

If you have 90 min:

helper With a helper

Segments that carry a job a helper can own, in timeline order. The adult keeps the iron, the blade, mains work and anything hot; the helper's job is named in the step itself.


By timeline row

1 · Both — Gen 2 joints and wiper, then pre-B00 checks, Gen 1 belts

  • wall-clock pause — see the timeline row for its gate

2 · Print — B00 — Calibration & jigs

3 · Build — Ch 00a — Mains safety

4 · Print — B01 — Z drive assemblies

5 · Print — B02 — Accent parts, the accent day

6 · Print — B03 — A/B drive units + front idlers

7 · Print — B04 — XY joints + X carriage

8 · Print — B05 — Z joints + Z chain

9 · Print — B06 — Toolhead: SB, CW2, Klicky

10 · Print — B07 — Electronics bay + lighting

11 · Print — B08 — Skirts and front modules

12 · Print — B09 — Panels, filtration, spool

13 · Print — B10 — Clicky-Clack door

14 · Build — Ch 00 — Before you start

15 · Build — Ch 12 Part 1 — image the Pi, install Klipper/Moonraker/Mainsail

16 · Build — Ch 01 — Frame

17 · Build — Ch 02 — Z drives, Z idlers, Z rails, deck

18 · Build — Ch 03 — Build plate

19 · Build — Ch 04 — A/B drives and front idlers

20 · Build — Ch 05 — Gantry

21 · Build — Ch 06 Part A — Z axis: hang the gantry, Z belts

22 · Build — Ch 07 — A/B belts, provisional tension

23 · Build — Ch 08 — Toolhead

24 · Build — Ch 09 — Electronics bay

25 · Build — Ch 10 — Wiring

26 · Build — Ch 12 Part 2 — flash both MCUs, printer.cfg for a 350 Rev D+

27 · Build — Ch 11 Part A — skirts, bay fans, bottom panel, Z belt covers, Nevermore, spool, door hinges

28 · Build — Ch 13 — Initial startup

29 · Build — Ch 06b — Gantry squaring, cold, and provisional tension

30 · Build — Ch 11 Part B — back, side and top panels, Clicky-Clack door

31 · Build — Ch 14 — Calibration and tuning: hot soak, final tension, re-check, then tune

32 · Print — B11 — Bay ducting, before kit

33 · Print — B11 — Bay ducting, after the kit-day measurements


Generated by scripts/build_tonight.py on every build — do not hand-edit. Plans are packed from the index timeline. On this device, segments you have ticked are skipped and each plan starts at your first unfinished step.