Batch B11Checkpoint

Checkpoint B11

Checkpoint · Batch B11 — Bay ducting (PETG V0)

  • Coupon lid snaps home and holds, tested before B11-P5
  • A/B leads confirmed after Checkpoint 06; a longer replacement lead made before Ch 10 if either was short
  • Leviathan-to-PSU gap measured: B11-P5 printed, or the fallback with LDO's PVC middle duct
  • SSR-to-WAGO measured; the stub regenerated at B11.11 if the gap was 112 mm or more
  • TH, probe, filter-fan and bed L leads confirmed against layout v3 in Ch 09/10, not on kit day
  • Every lid snaps onto its duct; bodies in 09-ducts-DC and 09-ducts-AC, lids in 10-lids-AC with the strip fin and 11-lids-DC
  • Smooth sheet back on the printer and Chamber Filtration on Adv. Filtration for any ASA plate
  • GUI QC done on all five plates and check_docs.py green after the re-saves
Revali passing a gate
Batch B11 printed: 5 plates, 25.0 h, outside the 157.0 h run. 5 gummy worms.

Common mistakes

  • Printing PETG V0 on the smooth sheet. It can tear the coating; use the textured sheet.
  • Printing B11-P5 before the coupon test and the gap measurement. Both can send it to the fallback.
  • Slicing a regenerated piece with the ASA bundle. B11 uses slicer/bay-ducts-petg.ini only.
  • Leaving Adv. Filtration to hold the flaps shut on a PETG plate printed without the B11 bundle.
  • Starting the next ASA plate with Chamber Filtration still on None. The AFS blower never runs, so the styrene goes into the room.

Next

Ch 09 fits the conduits in place of LDO's PVC ducts, in its bay-ducting variant; Ch 10 lays the harness in them and fits the strip fin as it closes the AC lids.