Step 05.1 — Clear the bench and confirm the sub-assemblies

Step 1 of 48 · Chapter 05 — Gantry: X and Y axes, XY joints, X carriage, titanium backers

Tap to enlarge

gather Gather for this segment — steps 05.1–05.4 (~25 min)

Printed parts

  • [a]_xy_joint_cable_bridge_2hole.stl (blue) ×1 · bin 05-XY

Set out for later steps

  • C extrusion ×2
  • D extrusion ×1
  • E extrusion ×1
  • M5 roll-in T-nut ×26
  • M3 roll-in T-nut ×58

Already on the bench

  • A drive assembly
  • B drive assembly
  • A idler assembly, front right
  • B idler assembly, front left

Parts:

  • A drive assembly · already on the bench
  • B drive assembly · already on the bench
  • A idler assembly, front right · already on the bench
  • B idler assembly, front left · already on the bench
  • C extrusion ×2 · set out now, fitted later
  • D extrusion ×1 · set out now, fitted later
  • E extrusion ×1 · set out now, fitted later

Do: Clear a bench at least 700 × 700 mm. Lay the four Ch 04 sub-assemblies out, drives at the top, idlers at the bottom. Keep the A drive on the right and the B drive on the left.

check Check

Four Ch 04 assemblies, each matching its CHECK YOUR WORK page: p.68 and p.72 idlers, p.76 and p.80 drives. All four spin freely.

What you're looking at

The gantry is the moving frame above the bed that carries the toolhead: a rectangle of extrusions whose X beam slides along two side rails. The page shows it finished, so you can see where the four Ch 04 sub-assemblies land at the corners.

Source: Voron manual p.82 · Video: Part 4 @0:06:30